An example of Critical Resource
Planning with a Flashboard
at a Pressed Metal
Component plant.
What is Critical
Resource Planning?
There
are many, many resources that have to be managed to make a business run.
But only
a few are critical "stop-the-ship" resources.
We know
that if these critical resources are managed well, the rest of the plan can
adapt.
Every
day, the key management group needs to get together
to make
sure that the day to day operation plan takes into account
any
changes in the need for the critical resources.
These
are often "outside the business" factors, such as tooling or special
long lead time materials.
When the
critical resource plan is visual, up on the wall, for everyone to see,
a quick
chat standing in front of the Flashboard is enough to keep everyone in the
picture.
No time
wasting, but everyone can work together.
If the
tooling department knows that the material is due in next week,
they
know that the tools will be needed and can anticipate... much better than
re-acting in rush mode.
Setting
up a Flashboard for Critical Resource Planning
In this
section, we will discuss how the Flashboard can be set up for critical
resources.
We will work
through an example of manual planning of critical resources.
Defining
Critical Resources
It is
important choose a small number of critical resources.
It is
better to be flexible and add and remove critical resources as the need arises.
For
example
Materials
Tooling
First
Operation
would be
a good starting point...
Usually,
a daily check of the critical resource plan is recommended,
which
means that one day would be the natural time unit.
For critical
resources the lead time would give the time range for the Flashboard.
With
special materials, eg imported, this
would give us a range of several months.
Practically,
the base model Flashboard provides for a range of 30 units. It could be set up
like this:
|
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
Pending |
The
pending area would hold strips for tasks more than five weeks away.
Strips
for Critical Resource Planning
One
strip is needed for each task on each critical resource.
This
would be directly related to production runs.
Production
runs would be triggered by customer orders for non-stock parts or by likely
stock out day for stocked parts.
Example.
A
customer order for part 123AA. Quantity 50,000
due 17/6.
Material: 52100 alloy, 500m
Tool: Die set AA
First
Op: Auto loader 3.5sec/part
We need
4 strips:
For the
run to fulfil the order:
|
Run Part
123AA 50,000 Due 17/6 >>| |
For the
material:
|
Material
52100 500m Part
123AA 50,000 Due 17/6 Lead
time offset 21 days >| |
For the
tooling:
|
Die
Set AA Part
123AA 50,000 Due 17/6 Lead
time offset 10 days >| |
For
first operation:
|
Forming 2 days Part
123AA 50,000 Due 17/6 Lead
time offset 7 days >>>>>>>>| |
Q. What accuracy is needed for the lead time
offset and run time?
A. Quick estimates by an experienced person are
best. Just to the nearest day.
Q. What is the >>>| at the bottom of the
strip?
A. A graphic representation of how much of our
own resource's time is involved in the task.
For something like material our own time
might only be a few minutes even if the supplier takes weeks to make it.
Q. How
long are the strips.?
A. Long enough to hold the writing and the
>>>>|, whichever is the longer.
Q. What about our 'bread and butter' work that
runs all the time?
A. If it doesn't impact on other work, and its
just business as usual, then
you can leave it off the critical resource
planning board.
(but, be
careful, for example, are you sure that there are no setups? )
Laying
out the Flashboard
The
strips are put up on the board backwards from the due date.
|
|
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
M |
T |
W |
T |
F |
Pending |
|
Reqd |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
123AA
17/6 >>>| |
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
First
Op |
|
|
|
|
|
|
|
|
|
|
123AA 17/6 >>>>>>>>| |
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tooling |
|
|
|
|
|
|
|
123AA 17/6 >| |
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material |
|
|
|
|
|
|
|
123AA 17/6 >| |
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Allowing
for capacity in Critical Resource Planning
As the strips
are put up, they can overlap.
For
example, you can obviously order several lots of material in one day.
However,
typically only so many parts can be active in First Op at a time.
In that
case, you could allocate several horizontal rows on the Flashboard to First Op.
without
designating specific machines.
For
example, if you have 3 operators and 5 machines,
you may
only be able to have 3 parts running at a time. In that case, use 3 rows for
First Op.
Planning
Critical Resources with the Flashboard
The
visual approach makes plan adjustments almost instinctive, for example.
Because
of some other change, extra work might be needed in first op.
A quick
look at the board show that 123AA is pending.
It can
be brought closer to today, but only if the material and tooling is brought up
as well.
If this
is done by the group, with all the players present,
and in
agreement, standing in front of the board, then we know we have a workable
plan.
Updating
the Flashboard
This is
the critical success factor in making it all work.
Everybody
concerned must make it their own personal responsibility that the board
properly reflects reality.
As tasks
are completed, the strips must be removed from the board. Dependent strips
should be updated.
In the
example above, when the tooling is ready, the tooling strip is pulled off the
board
and a
small blue tag is added to the first op strip.
This
signals that the run is now dependent only on material.
When the
material is delivered and checked, the material strip must be taken off the
board.
A small
green tag is added to the First Op strip.
Now
everyone can see that the 123AA is free to go in First Op
and the
finishing team should be ready to work on the parts in a couple of days time.